The control count is not the cost driver

Two organisations facing the same control set can be a factor of four apart on cost. The distance is in how well the estate is known and how many teams have to change what they do daily.

Serving Saudi Arabia from our Riyadh office and our engineering hubs in Lahore and Karachi

Market
Saudi Arabia
Written for
CIO, COO
Decision
Budget an ECC compliance programme
Languages
EN · AR

Cybersecurity credentials

  • National Cybersecurity Authority, Saudi Arabia

    NCA ECC

    ECC compliance expertise

    NCA registration

    Registered cybersecurity service provider

  • ISO

    ISO/IEC 27001

    ISO/IEC 27001 certified

Certifications & registrations

Cost drivers

Six variables, and which direction each pushes

Listed with the effect on effort, so a range quoted without reference to them can be recognised for what it is.

VariableEffect on priceWhy
Asset inventory qualityThe largest single factorAlmost every control is applied to a list of things. Where the list is incomplete, the control is applied to part of the estate and the finding arrives at the assessment. Building the inventory is often a third of the first programme and it is a prerequisite for pricing anything else honestly.
Number of teams that must changeRaises elapsed time more than costA control implemented by one platform team lands in weeks. The same control implemented across four business units lands in quarters, because the work is agreement rather than engineering.
Estate spreadMultiplies technical effortOne cloud account and one data centre is a different programme from three clouds, two data centres and an OT network. Each environment needs its own logging, identity and hardening evidence, and they rarely share tooling.
Evidence debtFront-loads the timelineControls that operate without producing a record have to be re-instrumented and then run for a period before the record means anything. That waiting period cannot be bought back, which is why it belongs at the start of the plan rather than the end.
Third-party populationAdds a workstream, not a taskSupplier controls mean contract review, questionnaires and follow-up with organisations that have no deadline of their own. Where the supplier count is in the hundreds, this is a programme in its own right and pricing it as a task is how timelines slip.
Whether you keep itDecides the cost of round twoControls built to pass once are rebuilt for the next cycle at close to full cost. Controls built to run produce their own evidence continuously, and the second assessment is a review rather than a project. The difference in the first programme is small; in the third it is most of the budget.

Ask any supplier quoting this

  • Which of these six drivers did you measure before quoting, and what did you find?
  • Is the asset inventory inside your scope or assumed to exist?
  • What happens to the price if the estate turns out to be larger than the brief said?
  • Who does the remediation — you, or us with your plan?

Reading a quote

A cheap assessment with expensive remediation behind it

The assessment is the visible line item and the cheap half. It is also the one most easily discounted, because a supplier who expects to win the remediation can price it at cost. That is not dishonest, but it does mean comparing assessment quotes tells you very little about what the programme will cost.

The number worth comparing is the remediation estimate against a named estate, with the assumptions written down. A supplier who will not give one before the assessment is being honest about uncertainty; a supplier who gives one without asking about the inventory is not.

Where budgets break

Three overruns that are predictable in advance

  1. 01

    The inventory arrives in month four

    Everything sequenced against it has to be revisited, and the controls already implemented are found to cover part of the estate. Building the inventory first looks like a delay and is the cheapest month in the programme.

  2. 02

    The operating period was not in the plan

    A control implemented in the last month has no operating history for the assessment to measure. Where the plan ends on implementation rather than on a period of running, the date is wrong by the length of that period.

  3. 03

    Suppliers were a line, not a workstream

    Third-party controls depend on organisations with no incentive to hurry. Where the supplier population is large, the response rate — not the effort — sets the date, and that is knowable at the start.

Our role

What a sizing engagement produces

  1. 01

    Establishing the position

    We read the published control text against what is actually running and record where you stand, in the words the assessment will use rather than in ours.

  2. 02

    Doing the work

    The remediation is ours — the engineering, the process change and the documentation — rather than a findings list handed to somebody else to implement.

  3. 03

    Leaving evidence behind

    Each control is set up to generate its own record as it runs, so the next assessment costs a fraction of this one.

The assessment that follows is your assessor's, and the plan is written so the budget survives contact with it.

The controls are published in full by the National Cybersecurity Authority. Work from that document rather than from a supplier's summary of it, and take applicability questions to the Authority or to your assessor. Source

Common questions

What buyers ask

Can you give a range without seeing our estate?+

Not a useful one. The honest range across organisations of similar headcount is wide enough that quoting it would be a guess wearing the clothes of an estimate. What we can do in a fortnight is measure the two drivers that decide most of it — inventory quality and how many teams have to change — and price against those.

Is it cheaper to do this internally?+

For the governance and evidence work, frequently yes, and organisations with a functioning internal audit team should consider it. The parts that are usually not cheaper internally are the technical remediation across an unfamiliar estate and the first scope definition, where the value of an outside reader is precisely that they do not share the assumptions that produced the gap.

How much of the first programme is reusable next cycle?+

Most of it, if the controls were built to run rather than to pass. The governance artefacts persist, the evidence generation persists, and what remains is a review of what changed. Where the first programme was assembled for a date, the second one costs close to the first, which is the most expensive way to be compliant twice.

Size the programme against your estate

A sized programme with the drivers named, so the budget conversation happens against your estate rather than against a market average.