The estate in one picture
Three telemetry streams that only mean something together
Each stream is already collected somewhere. The value is not new sensors; it is time-aligning what exists so a power event, a cooling response and an IT symptom read as one story.
Three telemetry inputs — power chain, cooling and environment, IT layer — converge into one time-aligned view, producing incidents with causes attached, visible trends, and tickets with evidence.
Power chain
Utility feed, generators, UPS, PDUs — load and health per branch.
Cooling and environment
CRAC/CRAH status, supply and return temperatures, humidity, leak detection.
IT layer
Server inlet temperatures, utilisation, and the alerts the NOC already watches.
What we do
One time-aligned view
Streams correlated on a shared timeline, with the rack as the unit both teams recognise.
An incident with its cause attached
The IT symptom arrives already linked to the facilities event behind it.
A trend instead of a surprise
Load and temperature creep is visible months before it becomes a constraint.
A ticket, not a screenshot
Alerts open work in the ticketing system with the evidence attached.
The category, honestly
DCIM is a discipline sold as a product
DCIM tools promise a single pane for assets, power, space and change, and the good ones can deliver much of it. What the brochure omits is that a DCIM platform is only as truthful as the data discipline behind it: an asset database that drifts from the racks, or thresholds copied from defaults, produce a confident dashboard that is quietly wrong. Buying the tool is the smallest part of the programme; keeping the model honest is the ongoing work.
Our advice is unfashionable: decide what questions the operation needs answered — which rack is nearest its power limit, which cooling unit is compensating for a neighbour, what changed before this alert — and evaluate any tool, DCIM or otherwise, against those questions. Some estates are served well by a full DCIM suite; others get further integrating the BMS, the PDU telemetry and the IT monitoring they already own. The question decides the tool, not the reverse.
Alert design
Alarms two teams can act on without translating each other
An alert is a designed object: it has an owner, a threshold with a reason, and an action. These are the rules that keep a shared alarm list from becoming a shared noise floor.
Every alert names its owner
A high-temperature alert on a rack goes to whoever can act — facilities if a cooling unit caused it, IT if a load change did — decided by the correlated data, not broadcast to both and owned by neither.
Thresholds carry their reasoning
A limit is set from the equipment rating, the design envelope or an observed baseline, and the reason is recorded next to it — so a threshold survives the person who set it and can be argued with later.
Severity is about time to act
Urgent means minutes before consequence; warning means days; information means a trend worth a look this week. Grading by consequence and time, not by which sensor fired, is what lets a night shift trust the page.
Suppression is designed, not improvised
During a planned maintenance window, the alerts that the work will trigger are suppressed by name and time, so the ones that still fire mean something. An operation that mutes alarms ad hoc is training itself to ignore them.
Capacity
Capacity trending answers next year’s question with this year’s data
The capacity question — when does this hall run out of power, cooling or space — is usually answered from nameplate figures and a spreadsheet updated at commissioning. Measured telemetry gives a better answer: actual draw per rack over months, cooling load against ambient conditions through a Gulf summer, and the growth rate of both. Trending that data turns capacity planning from an argument about assumptions into a reading of the estate’s own record, and it surfaces stranded capacity — power provisioned but never drawn — that the nameplate view hides.
Our role
What we integrate and what your shifts keep running
- 01
The telemetry inventory
We map every source the facility already has — BMS points, PDU feeds, sensors, IT monitoring — and what each can actually report, before recommending anything new.
- 02
The joined view and its alerts
We build the time-aligned view and design the alert model with facilities and IT in the same room, so thresholds, owners and severities are agreed rather than inherited from defaults.
- 03
The ticketing connection
Alerts open and update work in the ticketing and change tools you already run, with the telemetry evidence attached, so the monitoring layer joins the operation instead of adding a screen beside it.
The facility’s maintenance regime, escalation chain and operating limits are yours and stay yours; we make what the estate is doing visible in one place, so those decisions are made on the same evidence by everyone.
Common questions
What buyers ask
We already have a BMS and an IT monitoring stack. Why is that not enough?+
Because they answer different questions to different people and never meet. The BMS knows a cooling unit degraded at 14:02; the IT stack knows inlet temperatures climbed at 14:20 and a service throttled at 14:40. Each view is correct and neither contains the story. The work is not replacing either system — both stay — but aligning their data on one timeline with the rack as the shared unit, so the correlation that today happens in a post-incident meeting happens in the monitoring layer while there is still time to act.
Do we need a full DCIM suite, or can this be built on what we own?+
It depends on the questions you need answered, and we would rather establish those first. A large colocation estate managing thousands of assets, frequent customer changes and space-selling usually justifies a DCIM platform. A single enterprise facility often gets most of the value by integrating the BMS, PDU telemetry and IT monitoring it already owns into one view, at a fraction of the licence and data-maintenance burden. We have no commercial stake in either answer, which is precisely what makes the assessment useful.
Our alarm list is already too noisy. Will one view make it worse?+
Only if the alerts are merged without being redesigned, which is the mistake we exist to prevent. Joining the streams is the opportunity to rebuild the alert model: correlated events collapse into one alert with a cause instead of five symptoms, thresholds get reasons, every alert gets an owner, and planned work suppresses its own noise by name. Operations that do this typically end up with fewer pages that mean more, because the layer underneath is doing the correlation people used to do by ignoring things.
Can monitoring alerts open tickets in the service desk we already use?+
Yes, and it should be a requirement rather than a nice-to-have. An alert that opens a ticket with the telemetry evidence attached — the timeline, the correlated events, the affected racks — arrives as work someone is accountable for, in the queue the operation already manages. An alert that lives only on a wall screen depends on someone seeing it, remembering it and transcribing it. We integrate with the ticketing and change-management tools you run rather than introducing another queue.
In this cluster
Next step
Walk us through your estate
A telemetry walkthrough of your facility that lists every source — BMS, PDUs, sensors, IT monitoring — and marks which incidents of the last year would have been caught earlier had those sources shared one view.