- Market
- Saudi Arabia
- Written for
- CISO, Procurement
- Decision
- Plan the route to a certificate against a contract date
Credentials for Aramco compliance
NCA registration
Registered cybersecurity service provider

Aramco CCC
CCC certified

ISO/IEC 27001
ISO/IEC 27001 certified
The stages
Five stages, placed against the audit date
Fix the audit date first and place the work behind it. Fixing it last is what produces a schedule where every stage is on time and the certificate still arrives late.
1 · Scope determination — 2 to 3 weeks
The contracted work, the systems that touch it, the connections crossing the boundary, and the reasoning for what sits outside. Written to be read by the auditor. A boundary the auditor can accept or challenge before anything is bought.
2 · Readiness review — 3 to 4 weeks
Each applicable control against what exists in the scoped estate, with the evidence requirement identified at the same time rather than afterwards. A gap list where each item names its own closing evidence.
3 · Remediation — 6 weeks to 6 months
The range is this wide because of one variable: whether the estate is already segmented. Everything else is measured in weeks; separating a working estate is measured in months. Controls operating, each producing the record identified in stage two.
4 · Evidence window — set by the auditor
A period of the controls simply running and producing dated records. This is the stage no amount of resourcing compresses, and the reason the schedule is built backwards. A period of operation the audit can measure.
5 · Audit — conducted by the authorised firm
Selected from Aramco's published list. We are available to answer questions about the work we did; the audit itself, and the certificate, are theirs. A determination made by an independent party, which is the point.
Two starting positions
Where you start decides most of the date
Almost every supplier is in one of these two. The difference between them is not size, budget or headcount — it is one architectural fact.
| Option | What is already true | Where the months go | Realistic to audit | Biggest risk | Best for |
|---|---|---|---|---|---|
| Estate already separated | The contract systems sit behind their own boundary, access runs through a directory, some logging exists. | Documentation and evidence, not engineering. Most gaps close by writing something down and signing it. | Three to five months, most of it the evidence window. | Booking the audit before the evidence window has run. | Suppliers who have been through a certification before, or who built the estate recently. |
| One flat network | Contract work runs on the same network and often the same laptops as everything else. | Separating a working estate without interrupting delivery. Staged against a business that keeps operating. | Six to nine months. Shorter promises turn into a second audit booking. | Committing to the contract date before this is known, then discovering it in month four. | Nobody chooses this. It is where most suppliers find themselves, and naming it early is the whole point. |
Compressing it
What genuinely shortens this, and what only appears to
Two things shorten it legitimately. Narrowing the scope to what the requirement genuinely reaches, which most suppliers can do because most over-scope at first. And starting the evidence record on day one — turning on logging, running one access review, holding one exercise — so the window is already running while remediation happens rather than starting after it.
What does not shorten it is adding people to remediation, because the constraint is the evidence window rather than the work; or booking the audit earlier, because the audit measures a state and bringing it forward measures an earlier one. A supplier promising either is describing something that does not behave the way they are saying.
Our role
Which parts of the timeline we own
CCC readiness is a body of engineering, documentation and evidence work that has to be finished before an audit is worth booking. That work is ours.
- 01
Scope determination
Which of your systems perform the contracted work, which connections cross the boundary, and the reasoning for what sits outside it — written to be read by the assessor rather than by us.
- 02
Readiness review
Each requirement measured against what exists in the scoped estate, sorted by what it will take to close rather than by control number.
- 03
Remediation and documentation
The engineering work itself — segmentation, access control, logging, hardening — with the procedure and the ownership recorded as it is implemented rather than written up afterwards.
- 04
The realistic date
Where the achievable date falls later than the contract date we say so early, while there is still time to have that conversation with your customer rather than after it has become a delivery problem.
The audit then follows through an audit firm Saudi Aramco authorises for that purpose, selected from the published list, and we stay available through it to answer questions about the work we did.
Saudi Aramco publishes the requirement and maintains the list of firms authorised to conduct the audit. Take scope and applicability questions to your Aramco contract contact, and select the auditor from the published list rather than from a supplier's recommendation. Source
Common questions
What buyers ask
Can we book the audit now to hold a slot?+
Booking early to secure availability is sensible; treating the booked date as the plan is not. Authorised firms have finite capacity and lead times are real, so reserving a slot months out is prudent. What matters is that the date sits after the evidence window rather than after remediation, and that it can be moved if the readiness review finds the estate is in the second starting position above.
What happens if the audit finds gaps?+
You remediate and the finding is re-examined, which is normal rather than a failure — but it costs elapsed time and sometimes a second engagement of the auditor. The way to reduce that is a readiness review stricter than the audit rather than more generous: a review that accepts a described control without an artefact has moved the finding rather than closed it.
Does the certificate need renewing?+
It has a validity period, and the renewal terms come from Aramco rather than from us — your contract contact and the published programme material are the sources for that. What is worth planning for regardless: build the controls to be maintained rather than to pass once. Maintaining them is barely more expensive than passing, and it is much cheaper than rebuilding the evidence position from scratch when the renewal arrives.
In this cluster
Next step
Build the schedule backwards with us
A schedule with the audit date fixed first and the work placed behind it, so the customer conversation happens early.
Build the schedule backwards with us
What happens next
- 1We reply within one business day.
- 2A 30-minute scoping call with a senior consultant.
- 3A written proposal with scope, team, and timeline.
Or reach us directly
